Revision as of 19:54, 27 June 2022 by Camrenbt (talk | contribs) (Created page with "<!--Example Page --> <div style= "text-align:center;"> <!-- Add message here --> ''Message: Concrete bedding installs relatively quickly, without the need for compaction under pipe haunces'' </div> ----</br> <!-- Add body paragraphs here --> Concrete bedding was used successfully in this Montana dam. Placing and encasing the 170-ft, 48-inch concrete outlet conduit was estimated to cost $133,000 (2013 cost). Six days of work effort were required to construct the foundatio...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Message: Concrete bedding installs relatively quickly, without the need for compaction under pipe haunces



Concrete bedding was used successfully in this Montana dam. Placing and encasing the 170-ft, 48-inch concrete outlet conduit was estimated to cost $133,000 (2013 cost). Six days of work effort were required to construct the foundation of the spillway riser, excavate the outlet conduit trench, and place the outlet conduit (including concrete bedding placement).


Revision ID: 1662