Owner: Difference between revisions
No edit summary |
No edit summary |
||
Line 22: | Line 22: | ||
# Promptly notify the state dam safety program of any unusual observations. Unusual observations may be indications of distress; | # Promptly notify the state dam safety program of any unusual observations. Unusual observations may be indications of distress; | ||
# Inspect the dam and its appurtenances: | # Inspect the dam and its appurtenances: | ||
* On a regular periodic schedule based on size, condition, and consequence of failure, and; | *** On a regular periodic schedule based on size, condition, and consequence of failure, and; | ||
* During and after any unusual loading including, but not limited to, significant storm/runoff events or earthquakes, to determine if [[structural]] or operational problems exist; | *** During and after any unusual loading including, but not limited to, significant storm/runoff events or earthquakes, to determine if [[structural]] or operational problems exist; | ||
# Maintain records for the dam, including but not limited to [[construction]] plans and documents, [[engineering]] studies, inspection reports, monitoring records, photos, the emergency action plan, and the operation and maintenance manual; | # Maintain records for the dam, including but not limited to [[construction]] plans and documents, [[engineering]] studies, inspection reports, monitoring records, photos, the emergency action plan, and the operation and maintenance manual; | ||
# Obtain the services of an engineer or have qualified in-house staff to inspect the dam as required by state regulations."<ref name="MSDSP">[[Model State Dam Safety Program (FEMA P-316) | Model State Dam Safety Program (FEMA P-316), FEMA, 2007]]</ref> | # Obtain the services of an engineer or have qualified in-house staff to inspect the dam as required by state regulations."<ref name="MSDSP">[[Model State Dam Safety Program (FEMA P-316) | Model State Dam Safety Program (FEMA P-316), FEMA, 2007]]</ref> | ||
Line 40: | Line 40: | ||
{{Website Icon}} [https://damfailures.org/lessons-learned/regular-operation-maintenane-and-inspection-of-dams-is-important-to-the-early-detection-and-prevention-of-dam-failure/ Lesson Learned: Regular operation, maintenance, and inspection of dams is important to the early detection and prevention of dam failure (DamFailures.org)] | {{Website Icon}} [https://damfailures.org/lessons-learned/regular-operation-maintenane-and-inspection-of-dams-is-important-to-the-early-detection-and-prevention-of-dam-failure/ Lesson Learned: Regular operation, maintenance, and inspection of dams is important to the early detection and prevention of dam failure (DamFailures.org)] | ||
{{Website Icon}} [https://damfailures.org/lessons-learned/timely-warning-and-rapid-public-response-are-critical/ Lesson Learned: Timely warning and rapid public response are critical to saving lives during a dam emergency] | {{Website Icon}} [https://damfailures.org/lessons-learned/timely-warning-and-rapid-public-response-are-critical/ Lesson Learned: Timely warning and rapid public response are critical to saving lives during a dam emergency] | ||
<br/> | |||
==Best Practices Resources== | ==Best Practices Resources== | ||
{{Document Icon}} [[Model State Dam Safety Program (FEMA P-316) | Model State Dam Safety Program (FEMA P-316), FEMA, 2007]] | {{Document Icon}} [[Model State Dam Safety Program (FEMA P-316) | Model State Dam Safety Program (FEMA P-316), FEMA, 2007]] | ||
<br/> | |||
==Trainings== | ==Trainings== | ||
{{Video Icon}} [[On-Demand Webinar: The History of Dam Safety Governance in the US Including Risk Analysis]] | {{Video Icon}} [[On-Demand Webinar: The History of Dam Safety Governance in the US Including Risk Analysis]] |
Revision as of 16:03, 16 December 2022
Iron Bridge Dam on Lake Tawakoni in Texas. |
Ongoing Responsibilities
"A state inspection program depends on dam owners and/or their consultants to provide complimentary and necessary inspections and surveillance. The dam owner and heirs, successor, or assigns is ultimately responsible for the safety of the dam. The owner is directly responsible for the ongoing operation, maintenance, surveillance, and periodic inspection. The owner shall do all of the following:
- Provide for on-going surveillance of the dam. The level of surveillance will depend on the size, condition, and hazard classification of the dam;
- Train their personnel in the basics of visual inspection techniques. Any person employed by the owner who regularly visits or works at the dam should be trained to inspect part or all of the dam and to report any observed problems;
- Measure or read appropriate instrumentation and record and evaluate the data at specified time frames;
- Promptly notify the state dam safety program of any unusual observations. Unusual observations may be indications of distress;
- Inspect the dam and its appurtenances:
- On a regular periodic schedule based on size, condition, and consequence of failure, and;
- During and after any unusual loading including, but not limited to, significant storm/runoff events or earthquakes, to determine if structural or operational problems exist;
- Maintain records for the dam, including but not limited to construction plans and documents, engineering studies, inspection reports, monitoring records, photos, the emergency action plan, and the operation and maintenance manual;
- Obtain the services of an engineer or have qualified in-house staff to inspect the dam as required by state regulations."[1]
Responsibilities During Construction
"Partnering is the creation of an owner-contractor relationship that promotes achievement of mutually beneficial goals. By taking steps before construction begins to change the adversarial mindset, to recognize common interests, and to establish an atmosphere of trust and candor in communications, partnering helps to develop a cooperative management team. Partnering is not a contractual agreement and does not create any legally enforceable rights or duties. There are three basic steps involved in establishing the partnering relationship:
- Establish a new relationship through personal contact.
- Craft a joint statement of goals and establish common objectives in specific detail for reaching the goals.
- Identify specific disputes and prevention processes designed to head off problems, evaluate performance, and promote cooperation."[2]
Examples
Lesson Learned: A complete and thorough dam record is essential (DamFailures.org)
Best Practices Resources
Model State Dam Safety Program (FEMA P-316), FEMA, 2007
Trainings
On-Demand Webinar: The History of Dam Safety Governance in the US Including Risk Analysis
On-Demand Webinar: Human Factors in the Oroville Dam Spillway Incident
On-Demand Webinar: Risk Communication for Dams
On-Demand Webinar: Human Factors in Dam Failure and Safety
On-Demand Webinar: How to Communicate Effectively in Any Situation
On-Demand Webinar: Tolerable Risk Guidelines for Dams: How Safe is Safe Enough
On-Demand Webinar: Risk Assessment Basics for an Individual Dam
On-Demand Webinar: Risk Management for a Portfolio of Dams
Citations:
Revision ID: 5805
Revision Date: 12/16/2022